Installation
Step1: Drill holes in the wall with drill machine according to the size of bracket. Drill straight into the wall
do not shake the drill to avoid damage to the wall. Depth of the holes should be about 30mm and should
be the same in all the holes. After removing dust from the holes, measure the net depth of the holes. If
the depth is more than 33mm or less than 27mm, the expansion pipes can not be properly installed.
Position Min. clearance
Side
Top
Bottom
Front
30cm
30cm
30cm
10cm
Table 2 Minimum clearance needed
6.3 Preparation
6.4 Installation Steps
Following tools are needed for installation.
Installation Tools: Crimping tool, Plier, Screwdrivers and adjustable spanner and Drill machine.
Installation Tools
Inverter needs at least 30cm (see table 2) clearance. If this is not observed, inverter is likely to malfunction
high temperature inside the inverter. Samil Power will not cover any damage due to this condition.
Not exposed to direct cool air.
Not close to television antenna or antenna cable.
SolarRiver 2300TL~5200TL Models
Figure 9 Installation of Expansion Pipe