53
PVP250kW & PVP260kW Inverter
Installation & Operation Manual
B. Set the jumpers for the center inverters on the network.
• J7 - remove all three jumpers from the J7 pins for any inverter in the middle
of the network, and place the jumpers in the J16 neutral position.
J6 J16 J7
High X
Line X
Low X
Table 5-3 No Biasing or Termination (Default Setting)
C. Set the biasing.
Biasing sets the voltage levels on the data lines of an inactive or idle network.
It is very important that at least one device on the network provides biasing. On
shorter networks with fewer installed devices, biasing may only be needed on
the device furthest away from the master. Longer networks that are terminated
on both ends may require two devices to have their biasing enabled. To use the
inverter’s built-in biasing set the following jumpers:
• J7 - install a jumper on the rst pair of pins labeled “High”.
• J7 - install a jumper on the last pair of pins labeled “Low”.
J6 J16 J7
High X
Line X
Low X
Table 5-4 Biasing Enabled
Alternative: Terminate the network and enable biasing.
If an end inverter on the network requires both termination and biasing to be
enabled, set the following jumpers:
• J7 - install a jumper on the rst pair of pins labeled “High”.
• J7 - install a jumper on the rst pair of pins labeled “Line”.
• J7 - install a jumper on the last pair of pins labeled “Low”.
J6 J16 J7
High X
Line X
Low X
Table 5-5 Biasing and Termination Enabled (for End Device)